Before the next construction payment: what evidence should you request?

A date can trigger a reminder. A payment should be tied to an obligation.

Updated 16 July 2026
Sources and limitations

This page is not an official text or translation and is not legal, tax, accounting, immigration, financial, land/title or notarial advice. Reading it or sending a general enquiry does not create a professional-adviser relationship.

Rules, administrative interpretations and eligibility criteria can change. Check the update date, consult the applicable Bahasa Indonesia text in the official Indonesian regulations database, and obtain confirmation for your facts from the competent authority or an appropriately authorised Indonesian professional. If our summary differs from the official text or a confirmation for your file, do not rely on our summary. No permit, title, visa, tax treatment, return or other outcome is guaranteed.

Report a correction or outdated source: [email protected]. Any responsibility imposed by applicable law remains unchanged.

A date on the calendar is not proof of progress

A date can trigger a reminder. A payment should be tied to an obligation.

For each material instalment, the file should show:

  1. the contractual milestone;
  2. the approved drawings/specification and measurable scope behind it;
  3. current site evidence and measurement;
  4. inspection by a competent architect, engineer or quantity surveyor whose appointment and possible conflicts have been checked;
  5. the effect of defects, incomplete work, materials off site and previous overpayment;
  6. approved variations and time consequences;
  7. the correct invoice, tax, account and release authority;
  8. the balance and security remaining for completion, handover and defects.

The investor is not trying to micromanage a building site. The objective is simpler: do not let cash run materially ahead of verified value, control and remaining remedies.

Measurements that answer different questions

TermWhat it should meanWhat it is often confused with
Payment calendarForecast or fixed dates under a contractEvidence of completed work
Physical progressMeasured work completed to an agreed baselinePercentage of time elapsed or money spent
Cost incurredContractor/developer expenditureValue correctly installed for the investor
Material on siteIdentified material delivered, protected and allocatedCompleted, conforming work
Practical completionDefined level allowing agreed possession/use despite scheduled minor itemsPerfect completion, SLF, opening or final account
HandoverTransfer of defined possession, control, documents and riskAutomatic release of every remaining sum
RetentionContractually withheld amount with release rulesA universal statutory percentage or full protection
Warranty/defects periodTime and process for correcting covered defectsProof the responsible party will remain solvent and perform
Independent certificateOpinion within a named appointment and scopeGuarantee of title, legality, cost, all quality or future performance

Match each payment to evidence

Payment basisEvidence qualityMain riskBetter release rule
Date onlyNo site conditionCash can lead work substantiallyDo not convert a date into progress; add a measurable condition or consciously price the advance risk and security
Developer's percentageSelf-reportedMethod, conflicts and baseline unknownRequire supporting measurement and agreed independent review
Milestone name only (“structure complete”)Ambiguous scopeParties measure different workDefine inclusions, exclusions, tests, drawings and evidence
Measured work, no quality gateQuantity evidencedDefective work can still be paid in fullAdd inspection, test and defect treatment
Measured conforming workStrongerPrior overpayment, variations and completion funding may remainReconcile cumulative earned value, amounts paid and cost to complete
Materials off siteOwnership/control riskDouble sale, loss, non-delivery or incompatibilityTreat as payable only if the signed contract permits a defined ownership, identification, insurance, storage and delivery mechanism and the buyer accepts it with full knowledge; otherwise exclude
Handover certificateDelivery point evidencedMissing documents/licences/retention may be overlookedSplit physical, documentary, operational and final-account releases

There is no universal “correct” percentage schedule. A bespoke villa, a multi-unit estate, a land lease plus build and a completed-unit sale do not carry the same risks. What can be universal is the discipline: define the trigger, evidence it, reconcile the money, preserve enough leverage to finish.

For a transaction that falls within the housing PPJB rules in PP 12/2021, keep two thresholds separate. The 20% construction test is one of the conditions that must be satisfied before the PPJB stage. For detached or row houses, it concerns at least 20% of all planned units plus the planned infrastructure, facilities and utilities; for an apartment building, it concerns 20% of the building's construction volume. It is not 20% of the buyer's villa and not a standard payment milestone. Separately, the developer may not collect more than 80% until the relevant PPJB conditions are satisfied. That limit is not a statutory escrow account. Counsel must first confirm that the housing PPJB rules apply to the transaction.

Agree the baseline before measuring progress

You cannot measure a render.

The payment baseline should include, as applicable:

  • signed contract and complete party/capacity details;
  • issued-for-construction architectural, structural and MEP drawings;
  • specification and approved material/equipment schedule;
  • bill of quantities, schedule of values or other measurement basis;
  • programme with critical approvals, utilities, procurement and commissioning;
  • responsibility matrix;
  • approved contract price and contingency treatment;
  • definition of each milestone and required evidence;
  • inspection, notice, payment and dispute timetable.

If the design remains intentionally incomplete, the contract must expose that uncertainty. It should not present a fixed price and fixed delivery date while leaving the most expensive details to later “client upgrades”.

Five checks before payment

  1. Written request: amount due, contractual milestone, invoice, payee, bank account, supporting documents and cumulative payment position.
  2. Site evidence: dated inspection record, photographs tied to locations, test results, delivery records and an updated schedule.
  3. Independent review: a competent architect, engineer or quantity surveyor checks only the work covered by their written appointment and states any exclusions or conflicts.
  4. Contract check: confirm the milestone, approved changes, delay notices, outstanding defects, security and the estimated cost and time still needed to finish.
  5. Payment record: pay only to the verified contractual account after the authorised decision-maker approves it, then retain the certificate, invoice, payment confirmation and conditions for the next instalment.

Changes: when a fixed budget stops being fixed

A variation should answer five questions before work, except under a tightly defined emergency procedure:

  1. What changed, and why?
  2. Who had authority to instruct it?
  3. What drawing/specification replaces the old one?
  4. What is the price basis and tax effect?
  5. What is the programme and completion impact?

Maintain one register:

IDInstructionScopePriceTimeStatusEvidence
V-01Drainage redesignRevised civil drawingPending QS review+? daysNot approvedSite/engineer note
V-02Stone substitutionNamed equivalentIDR …0ApprovedSample + signed order

“Included in next invoice” is not a variation process. Nor should the investor be asked to approve price after the replacement is already concealed in the work.

Money withheld until completion, and other security

Retention can preserve money until defined completion and defect gates. It is only as good as its drafting:

  • percentage/base;
  • cap;
  • who holds it;
  • first release trigger;
  • second/final release trigger;
  • right to apply it to uncorrected defects;
  • insolvency and termination treatment;
  • interaction with bonds, guarantees and final account.

It is not always present and no percentage should be described as universally required.

Likewise, an advance-payment guarantee, performance bond, bank guarantee, escrow or parent guarantee must be read as an instrument, not as a label. Check issuer, beneficiary, amount, expiry, reduction, demand conditions, defences, governing law and whether the security survives the period when risk exists.

Handover has four separate parts

ReleasePossible conditionsWhy separate it?
Practical/physical completionInspected work substantially complete; punch list definedPossession may be possible before every minor defect is fixed
Documentary completionAs-builts, manuals, warranties, test records, approvals/SLF route as applicableAn undocumented villa is expensive to operate, insure, repair and sell
Operational readinessUtilities, staff/vendor handover, operator/licensing/tax/merchant dependenciesA finished building may not be a functioning accommodation business
Final account/defects releaseFinal variations settled; defects corrected; retention conditions metKeeps the close-out dispute from contaminating possession and opening

The contract may structure these differently. The analytical point is that one signature should not accidentally certify four different things.

Example: replace six calendar payments with five evidenced stages

All entities, percentages, dates and facts in this worked example are fictional and illustrative.

The brochure proposes:

  • 20% reservation/signing;
  • 20% after 60 days;
  • 20% after 120 days;
  • 20% after 180 days;
  • 15% at “completion”;
  • 5% at key handover.

The reviewed structure might instead distinguish:

  1. Initial release: transaction/land authority, reviewed contract, baseline and essential pre-construction conditions satisfied; any true advance separately secured or consciously priced.
  2. Substructure gate: measured and tested foundations/substructure under approved structural documents, with cumulative certificate.
  3. Weather-tight structure gate: defined structure, roof and envelope complete to specification; concealed tests/inspections filed.
  4. MEP and finishes gate: first/second fix and finishes measured by package; commissioning dependencies and variations reconciled.
  5. Handover and close-out: physical completion release, separate documents/operational conditions, then retention/defect release.

Dates remain in the programme and longstop remedies. They stop pretending to be evidence of construction.

Limits of this payment check

It does not:

  • create a right to withhold, inspect, enter the site or terminate if the contract lacks it;
  • decide which housing/PPJB or construction rules apply to your transaction;
  • make the certifier independent or liable without a proper appointment;
  • detect hidden defects without the required inspections/tests;
  • guarantee completion, funding or contractor solvency;
  • make escrow, bonds, retention or milestone payments universally mandatory;
  • replace land, permit, tax, insurance or operating due diligence;
  • determine the tax invoice/withholding/VAT answer without the exact parties and supply.

Build a record for the next payment

Use the Bali property due diligence guide to organise the project evidence before assessing a payment request. Review construction quotes and scope, then test how the construction period and remaining leasehold term affect the exit assumptions.

Before the next transfer, ask for one complete, well-organised file containing the cumulative certificate, current site evidence, the approved variation register, payment reconciliation, an updated cost and completion forecast, and the conditions that must be met before the following payment. This is a standard request for evidence.

Official sources and date consulted

Official sources consulted on 15 July 2026. Official anchors: PP 16/2021 for the building system and distinct PBG/SLF functions; Permen PU 6/2025 for the current construction-business/workforce certification framework; Permen PKP 18/2025 for housing-sector business standards within scope; Permen PUPR 24/2018 for its housing-developer certification/registration framework; SE 05/SE/Dp/2026 for the SIRENG service and its stated government-assisted/financed/incentivised housing monitoring context; SE 06/SE/Dp/2026 separately for formats/mechanisms of applicable housing-business obligations and sanctions; PP 12/2021 for the housing/PPJB framework where it applies. The relationship between Permen PUPR 24/2018, SE 05/2026 and current SIRENG coverage requires confirmation from the relevant Indonesian professionals. No registry result should be treated as project approval, a whitelist or proof of title, solvency, payment protection, delivery, quality or safety.

The milestone, retention, variation, security and handover measures above are contractual safeguards, not a claim that Indonesian law imposes one universal model. Before using them, have Indonesian counsel examine the transaction and contract, agree the inspection and payment procedure with the appointed architect, engineer or quantity surveyor, confirm the construction qualifications required for each work package, obtain Indonesian tax advice on the payments, and have every bank instrument or security examined. Reopen the official sources on the decision date.

From information to a project decision

Is this question part of a real Bali residence project?

Share the site, capital and decision context in a private brief. DALLEAU will identify the most useful owner-side next step; regulated legal, tax, immigration and notarial matters remain with authorised advisers.

Start a private brief

Follow material changes

Receive a short email when a Field Note is published or materially revised.